SOLAR POWER PLANTS OF ZAKARPATTIA

The solar power plant is designed for industrial generation of electricity by converting solar energy into environmentally friendly electricity in solar photovoltaic modules with its subsequent transformation into external electrical networks of the Transcarpathian regional region. 

The purpose of this project is the decentralization of energy in Ukraine.

The designed stations occupy plots with a total area of ​​over 50 hectares;

The projected estimated capacity of the stations totals over 20,000 kW;

  • Estimated estimated annual electricity generation is more than 24,000 MWh/year. 
  • Svitovyr developed various sections of projects. 
  • With an individual approach to each SES in accordance with the requirements of the Customer and technical conditions for the connection of issued PJSC "Zakarpattiaoblenergo".


SOLAR POWER PLANTS OF LVIV REGION

The dynamic growth of photovoltaic modules, improvement of their efficiency and improvement of production technology has led to a reduction in the cost of construction of solar power plants. Which in turn is one of the main factors why solar energy is currently one of the most intensively developing renewable energy sectors. In addition, solar energy is environmentally friendly, PPS do not have a negative impact on the environment. 

Some of the most developed countries in the world (Baltic states, Germany, China…) attach strategic importance to alternative energy, as it leads to energy independence of the state (reduces dependence on imports of oil, gas, coal, etc.). Thanks to government support and significant production volumes in countries such as Chile, Australia, Mexico, and Germany, solar energy has become cheaper than energy obtained from traditional (oil, gas, coal) sources.

Unlike traditional power plants, solar power plants do not need to be located near rivers and reservoirs. This makes it possible to build PPS anywhere, including in areas contaminated by former enterprises (former quarries, landfills, etc.) and on lands unsuitable or unsuitable for agriculture. Svitovyr will take an active part in the development of alternative energy sources.

In particular, the Svitovyr team took an active part in the development of projects in full or in part of the projects of the following stations of Lviv region: 

- Photoelectric solar power plant "Nagirne-1"; 
- Photoelectric terrestrial solar power plant "Nagirne-2";
- Solar power plant in the village. Kulykiv, Zhovkva district, Lviv region;
- Photoelectric terrestrial solar power plant "Shchyrets-1";
- Photoelectric terrestrial solar power plant "Shchyrets-2" (I and II turn);
- Photoelectric terrestrial solar power plant FES "Semenivka";
- SOLAR POWER PLANT-1 in the village of Dobrivlyany, Stryj district, Lviv region”;
- SOLAR POWER PLANT-2 in the village of Dobrivlyany, Stryi district, Lviv region;
- SOLAR POWER PLANT-3 in the village of Dobrivlyany, Stryj district, Lviv region.


SOLAR POWER PLANTS OF THE CARPATHIAN

The photovoltaic power station is designed for industrial generation of electricity by converting solar energy into environmentally friendly electricity in solar photovoltaic modules with its subsequent transformation into external electrical networks of the Carpathian region. 

The purpose of this project is the decentralization of energy in Ukraine.

General description of the station:
- the projected station is located on a plot of 4.98 hectares;
- the estimated design power of the station is 2494.8 kW;
- projected estimated average annual electricity generation - 2703 MW / h / year. 

 The project envisages the following stages of construction of SES New construction of SES 2000 kW in the tract "Mountain" with. Myshyn, Kolomyia district, Ivano-Frankivsk region ”: 

  • Arrangement of accounting of SES "Myshyn".
  • Construction of 10 kV distribution networks. 
  • 0.4 kV network. 
  • Designing consumers' own needs of SES. DC networks. 
  • Automation and control system.


INSTALLATION OF THE DISCONNECTOR ON GRP 220 KV

The project was developed for DTEK BURSHTYNSKA TPP (within the program “Change of the connection scheme of SS-1A 220 kV to SS-1B 220 kV”). 

A number of tasks were performed:

  • execution of project documentation 
  • dismantling of the 220 kV disconnector 
  • installation of a 220 kV disconnector 
  • performance of start-up and adjustment works


IMPLEMENTATION OF SINGLE-PHASE LOCK PROTECTION SYSTEM

Introduction of a system of protection against single-phase earth faults in networks of 6 kV VP 5 approx. DTEK Burshtyn TPP (with the use of ALTRA devices). 

A number of works performed within the project: 

  •  execution of project documentation; 
  •  installation of protection system (“ALTRA” devices); 
  • organization of data transmission network; 
  • performance of commissioning works.


REPLACEMENT OF THE 110 KV SWITCH WITH GPP-110/35/6

REPLACEMENT OF 110 KV SWITCH WITH GPP-110/35/6 KVPAT STEBNYTSK MINING AND CHEMICAL ENTERPRISE "POLYMINERAL"

A number of works were performed: 

  • execution of project documentation;
  • dismantling of the 110 kV switch ;
  • installation of the 110 kV 120-SFM-32B SF6 switch SFM-SFM-32B 32B (CG Power Systems), busbar installation; 
  • performance of start-up and adjustment works.